MasterFormat (maintained jointly by CSI and CSC — it's a Canadian standard as much as an American one) organizes specifications into numbered divisions, each holding sections numbered DD SS SS. Two working rules before the list: your scope is never entirely inside "your" division — Division 01 binds everyone, and cross-division items (your access hatch in their wall) are routine; and read codes as families — a spec's "07 26 16" belongs to the "07 26" family whether your reference list carries the exact code or not.

Procurement and general

Div.TitleEstimator's note
00Procurement and Contracting RequirementsBid forms, instructions to bidders, contract conditions. The deal-breakers live here — read before pricing anything
01General RequirementsBinds every trade: temporary services, cleaning, closeout, testing, protection. The seven costly clauses →

Facility construction (02–14)

Div.TitleEstimator's note
02Existing ConditionsDemolition, abatement designations, investigation reports — renovation money and renovation risk
03ConcreteCIP, precast, toppings; exposure classes and FF/FL live here (with CSA A23.1 doing the governing)
04MasonryUnit masonry, veneer, mortar and accessories
05MetalsStructural steel, joists, deck — and 05 50 misc. metals, the classic scope-boundary dispute zone
06Wood, Plastics and CompositesRough carpentry, blocking and backing (everyone's problem), millwork
07Thermal and Moisture ProtectionRoofing, waterproofing, insulation, air barriers, firestopping, sealants — the building-envelope catch-all
08OpeningsDoors, frames, hardware, glazing, curtain wall
09FinishesDrywall, ceilings, flooring, paint — and the substrate-prep clauses that reach back into Division 03
10SpecialtiesPartitions, lockers, signage — small sections, easy to miss, someone has to carry them
11EquipmentOwner equipment with trade-supplied bases, backing and rough-in — coordination items breed here
12FurnishingsUsually NIC, but check who anchors and who patches
13Special ConstructionPre-engineered buildings, pools, vaults — self-contained scopes with tentacles
14Conveying EquipmentElevators and hoists — plus the pits, rails and machine-room work other trades carry for them

Facility services (21–28)

Div.TitleEstimator's note
21Fire SuppressionSprinklers and standpipes
22Plumbing
23HVACThe thickest division on most institutional jobs
25Integrated AutomationBuilding controls — watch the boundary with 23 and 26
26ElectricalPower and lighting; the starter/VFD/disconnect ownership question vs. Division 23 is a perennial leveling dispute
27CommunicationsStructured cabling, AV
28Electronic Safety and SecurityFire alarm, access control, cameras

Site and infrastructure (31–35)

Div.TitleEstimator's note
31EarthworkExcavation, backfill, shoring — read alongside the geotech report, which is the real bid document
32Exterior ImprovementsPaving, curbs, landscaping — the sitework/building-trade boundary lives here
33UtilitiesSite services to the building line

Process divisions (40–48)

Industrial work — process piping (40), material handling (41), process heating/cooling (42), gas and liquid handling (43–46), electrical power generation (48). Most ICI building tenders never open these; industrial ones live in them. If your building tender cites a 40-series section, read it — it usually means owner process equipment with trade interfaces.

The numbering traps

  • Two eras. Pre-2004 MasterFormat used five digits and 16 divisions (03300 = cast-in-place concrete); the current edition uses six digits and the 00–48 structure. Owner in-house standards and older reference documents still carry five-digit codes — same families, different shape. Indexing a manual that mixes both →
  • The moved divisions. The classics that changed homes in 2004: mechanical's old Division 15 became 21–23, electrical's old 16 became 26–28. An older estimator's "Div 15/16" and a current spec's "Div 21–28" are the same conversation.
  • Reserved gaps. Divisions like 15–20, 24, 29–30 and others are reserved — a spec using one is either an owner's custom structure or an error, and either way worth a closer look.
  • Section-level scope beats division-level scope. Bidding "Division 9" is how drywall ends up priced by the flooring sub. Real scope statements name section families — which is also how modern tools (ours included) filter what gets read.