The division list as it actually shows up in Canadian ICI tenders — with notes on where each trade's money hides, and the numbering traps between the old five-digit world and the current one.
MasterFormat (maintained jointly by CSI and CSC — it's a Canadian standard as much as an American one) organizes specifications into numbered divisions, each holding sections numbered DD SS SS. Two working rules before the list: your scope is never entirely inside "your" division — Division 01 binds everyone, and cross-division items (your access hatch in their wall) are routine; and read codes as families — a spec's "07 26 16" belongs to the "07 26" family whether your reference list carries the exact code or not.
Procurement and general
| Div. | Title | Estimator's note |
| 00 | Procurement and Contracting Requirements | Bid forms, instructions to bidders, contract conditions. The deal-breakers live here — read before pricing anything |
| 01 | General Requirements | Binds every trade: temporary services, cleaning, closeout, testing, protection. The seven costly clauses → |
Facility construction (02–14)
| Div. | Title | Estimator's note |
| 02 | Existing Conditions | Demolition, abatement designations, investigation reports — renovation money and renovation risk |
| 03 | Concrete | CIP, precast, toppings; exposure classes and FF/FL live here (with CSA A23.1 doing the governing) |
| 04 | Masonry | Unit masonry, veneer, mortar and accessories |
| 05 | Metals | Structural steel, joists, deck — and 05 50 misc. metals, the classic scope-boundary dispute zone |
| 06 | Wood, Plastics and Composites | Rough carpentry, blocking and backing (everyone's problem), millwork |
| 07 | Thermal and Moisture Protection | Roofing, waterproofing, insulation, air barriers, firestopping, sealants — the building-envelope catch-all |
| 08 | Openings | Doors, frames, hardware, glazing, curtain wall |
| 09 | Finishes | Drywall, ceilings, flooring, paint — and the substrate-prep clauses that reach back into Division 03 |
| 10 | Specialties | Partitions, lockers, signage — small sections, easy to miss, someone has to carry them |
| 11 | Equipment | Owner equipment with trade-supplied bases, backing and rough-in — coordination items breed here |
| 12 | Furnishings | Usually NIC, but check who anchors and who patches |
| 13 | Special Construction | Pre-engineered buildings, pools, vaults — self-contained scopes with tentacles |
| 14 | Conveying Equipment | Elevators and hoists — plus the pits, rails and machine-room work other trades carry for them |
Facility services (21–28)
| Div. | Title | Estimator's note |
| 21 | Fire Suppression | Sprinklers and standpipes |
| 22 | Plumbing | — |
| 23 | HVAC | The thickest division on most institutional jobs |
| 25 | Integrated Automation | Building controls — watch the boundary with 23 and 26 |
| 26 | Electrical | Power and lighting; the starter/VFD/disconnect ownership question vs. Division 23 is a perennial leveling dispute |
| 27 | Communications | Structured cabling, AV |
| 28 | Electronic Safety and Security | Fire alarm, access control, cameras |
Site and infrastructure (31–35)
| Div. | Title | Estimator's note |
| 31 | Earthwork | Excavation, backfill, shoring — read alongside the geotech report, which is the real bid document |
| 32 | Exterior Improvements | Paving, curbs, landscaping — the sitework/building-trade boundary lives here |
| 33 | Utilities | Site services to the building line |
Process divisions (40–48)
Industrial work — process piping (40), material handling (41), process heating/cooling (42), gas and liquid handling (43–46), electrical power generation (48). Most ICI building tenders never open these; industrial ones live in them. If your building tender cites a 40-series section, read it — it usually means owner process equipment with trade interfaces.
The numbering traps
- Two eras. Pre-2004 MasterFormat used five digits and 16 divisions (03300 = cast-in-place concrete); the current edition uses six digits and the 00–48 structure. Owner in-house standards and older reference documents still carry five-digit codes — same families, different shape. Indexing a manual that mixes both →
- The moved divisions. The classics that changed homes in 2004: mechanical's old Division 15 became 21–23, electrical's old 16 became 26–28. An older estimator's "Div 15/16" and a current spec's "Div 21–28" are the same conversation.
- Reserved gaps. Divisions like 15–20, 24, 29–30 and others are reserved — a spec using one is either an owner's custom structure or an error, and either way worth a closer look.
- Section-level scope beats division-level scope. Bidding "Division 9" is how drywall ends up priced by the flooring sub. Real scope statements name section families — which is also how modern tools (ours included) filter what gets read.
Your divisions, indexed on upload
Tender Helper splits every project manual by division with page ranges the moment it's uploaded — set your scope by trade, and only those sections get read, in full.