Each of the 25 checklists below covers one trade's real scope — what's actually theirs, what's routinely written into someone else's section instead, and what gets missed because of it. They're grouped by CSI MasterFormat division, same as a project manual, so if you already know which division your dispute lives in, you can go straight there.

Six of these boundaries come up often enough — and cut across enough trades — that they got their own longer, deeper treatment instead of a paragraph inside a trade page. Those are linked at the bottom, under "Read further."

Division 02 — Existing Conditions

TradeWhere it usually bites
DemolitionThe designated-substances survey is the real bid, not the demolition drawings

Division 03 — Concrete

TradeWhere it usually bites
Concrete formingWho owns placing and vibration decides who owns honeycombing found at strip
Reinforcing steelEmbeds — anchor bolts, sleeves, connection plates — sit in no trade's scope more often than any other single gap
Concrete supplyThe exposure class table that sets your mix price is usually on the S-sheets, not in the concrete section
Concrete finishingThe FF/FL numbers that actually price the job routinely hide in Division 01

Division 04 — Masonry

TradeWhere it usually bites
MasonryLoose lintel supply is steel's, installation is masonry's — on most sets, not all

Division 05 — Metals

TradeWhere it usually bites
SteelBase plate grouting is the single most litigated gap between steel and concrete
Miscellaneous metalsA bollard on the civil sheet, a ladder on the mechanical detail — none of it lives near the metals spec

Division 06 — Wood, Plastics and Composites

TradeWhere it usually bites
Rough carpentryThe backing every other trade assumes you'll frame in is never handed to you as a list
MillworkBacking is drywall's material, but its location comes from millwork's own shop drawings

Division 07 — Thermal and Moisture Protection

TradeWhere it usually bites
WaterproofingA 14 to 28 day concrete cure precondition, stated once, can own your whole schedule
RoofingThe curb sizes that drive your flashing labour usually sit in someone else's section
FirestoppingDivisions 21–28 routinely disclaim it at their own penetrations by default
CladdingThe panel schedule prices the panels — not everything around them

Division 08 — Openings

TradeWhere it usually bites
Doors and hardwareWhether this trade installs what it supplies changes tender to tender
GlazingSlab-edge fire safing at curtain wall gets claimed — or disclaimed — by two packages at once
Specialty doorsThe run from disconnect to motor gets argued on nearly every job that has one

Division 09 — Finishes

TradeWhere it usually bites
DrywallThe Level 5 finish clause is hiding in the painting section
FlooringMoisture testing decides who pays, and the curing-compound clause is in concrete's section
PaintingThe clause deciding whether Level 4 drywall finish is acceptable is written here, not in drywall's section
Interior finishesDemountable partitions are routinely a separate supplier-installed system hiding inside this section

Division 14 — Conveying Equipment

TradeWhere it usually bites
Conveying equipmentThe hoistway tolerance clause is the single most common delay claim on an elevator job

Divisions 21–23 — Mechanical

TradeWhere it usually bites
MechanicalEvery scheduled unit needs a starter, VFD or disconnect, and the schedule almost never says whose

Division 26 — Electrical

TradeWhere it usually bites
ElectricalThe Division 23/26 starter boundary and fire alarm's four duties both live here

Divisions 31–33 — Site and Infrastructure

TradeWhere it usually bites
Site workThe geotechnical report is the real bid document, and the rock line depends entirely on how "rock" is defined

Read further

Some boundaries above show up often enough, and cross enough trades, to deserve more than a paragraph: