Every trade checklist on this site, organized the way a project manual is — by CSI division — so you can find the one boundary dispute you're actually trying to settle without reading all 25.
Each of the 25 checklists below covers one trade's real scope — what's actually theirs, what's routinely written into someone else's section instead, and what gets missed because of it. They're grouped by CSI MasterFormat division, same as a project manual, so if you already know which division your dispute lives in, you can go straight there.
Six of these boundaries come up often enough — and cut across enough trades — that they got their own longer, deeper treatment instead of a paragraph inside a trade page. Those are linked at the bottom, under "Read further."
Division 02 — Existing Conditions
| Trade | Where it usually bites |
| Demolition | The designated-substances survey is the real bid, not the demolition drawings |
Division 03 — Concrete
| Trade | Where it usually bites |
| Concrete forming | Who owns placing and vibration decides who owns honeycombing found at strip |
| Reinforcing steel | Embeds — anchor bolts, sleeves, connection plates — sit in no trade's scope more often than any other single gap |
| Concrete supply | The exposure class table that sets your mix price is usually on the S-sheets, not in the concrete section |
| Concrete finishing | The FF/FL numbers that actually price the job routinely hide in Division 01 |
Division 04 — Masonry
| Trade | Where it usually bites |
| Masonry | Loose lintel supply is steel's, installation is masonry's — on most sets, not all |
Division 05 — Metals
| Trade | Where it usually bites |
| Steel | Base plate grouting is the single most litigated gap between steel and concrete |
| Miscellaneous metals | A bollard on the civil sheet, a ladder on the mechanical detail — none of it lives near the metals spec |
Division 06 — Wood, Plastics and Composites
| Trade | Where it usually bites |
| Rough carpentry | The backing every other trade assumes you'll frame in is never handed to you as a list |
| Millwork | Backing is drywall's material, but its location comes from millwork's own shop drawings |
Division 07 — Thermal and Moisture Protection
| Trade | Where it usually bites |
| Waterproofing | A 14 to 28 day concrete cure precondition, stated once, can own your whole schedule |
| Roofing | The curb sizes that drive your flashing labour usually sit in someone else's section |
| Firestopping | Divisions 21–28 routinely disclaim it at their own penetrations by default |
| Cladding | The panel schedule prices the panels — not everything around them |
Division 08 — Openings
| Trade | Where it usually bites |
| Doors and hardware | Whether this trade installs what it supplies changes tender to tender |
| Glazing | Slab-edge fire safing at curtain wall gets claimed — or disclaimed — by two packages at once |
| Specialty doors | The run from disconnect to motor gets argued on nearly every job that has one |
Division 09 — Finishes
| Trade | Where it usually bites |
| Drywall | The Level 5 finish clause is hiding in the painting section |
| Flooring | Moisture testing decides who pays, and the curing-compound clause is in concrete's section |
| Painting | The clause deciding whether Level 4 drywall finish is acceptable is written here, not in drywall's section |
| Interior finishes | Demountable partitions are routinely a separate supplier-installed system hiding inside this section |
Division 14 — Conveying Equipment
| Trade | Where it usually bites |
| Conveying equipment | The hoistway tolerance clause is the single most common delay claim on an elevator job |
Divisions 21–23 — Mechanical
| Trade | Where it usually bites |
| Mechanical | Every scheduled unit needs a starter, VFD or disconnect, and the schedule almost never says whose |
Division 26 — Electrical
| Trade | Where it usually bites |
| Electrical | The Division 23/26 starter boundary and fire alarm's four duties both live here |
Divisions 31–33 — Site and Infrastructure
| Trade | Where it usually bites |
| Site work | The geotechnical report is the real bid document, and the rock line depends entirely on how "rock" is defined |
Read further
Some boundaries above show up often enough, and cross enough trades, to deserve more than a paragraph:
- The Division 23/26 boundary, exhaustively — starters, VFDs, disconnects, duct detectors, and interlock wiring, checked unit by unit.
- Fire alarm's four duties — why bids miss one — device installation, wiring, programming, and verification, and why the last two fall through together.
- The geotechnical report as the real site-work bid document — rock, unsuitable material, dewatering, and how to read one in 20 minutes.
- How construction scope disputes actually get resolved — the patterns that repeat across every trade above, in one piece.
- Construction tender terms, for Canadian ICI subcontractors — the vocabulary these checklists assume you already know.
- CCDC contracts, plainly — what a subcontractor actually needs to know about the standard-form contract most of these tenders sit on.
Every division, read in full
Tender Helper reads the whole document, not just the division you tell it to watch — so a clause sitting in the wrong section still reaches your scope list.